Milestone timeline

 

Milestone

Date

Enumeration date

4 January 2021

Confirmation from the Commissioner that the statutory process is underway and launch of LGBC website

February  2021

Preparation of provisional proposals, data analysis, mapping

February – May 2021

Launch of provisional proposals

27 July 2021

Closing date for written representations on provisional proposals

21 September 2021 (8 weeks)

Public hearings

w/c 27 September

w/c 4 October 2021

Analysis of public hearing reports and representations made to the commissioner on Provisional Proposals.  Preparation of revised proposals

September – December 2021

Launch of public consultation on revised proposals

January 2022

Close of public consultation on revised proposals

February 2022

Publication of commissioner's report May 2022